Successful Engine Runs for Boeing 747-8 Intercontinental

On Mar. 9, Boeing has successfully completed the first engine runs for the 747-8 Intercontinental. The milestone marks a key step in preparing Boeing’s largest-ever passenger jet for flight test.

Elizabeth Lund, vice president and deputy program manager of the 747 program, said, “The integrated airplane systems and engines performed as expected,” adding, “This result allows us to continue moving forward to first flight.”

Engine runs began at 11:57 a.m. (PST) Tuesday and lasted approximately two hours and 45 minutes. During initial engine runs, the engines are started and operated at various power settings to ensure all systems perform as expected. The engine run test began with the Auxiliary Power System providing power to start the first of four GE GEnx-2B engines. The remaining three engines were started using the cross-bleed function.

Basic systems checks continued throughout the test. The engines were powered down and inspected and will be restarted following a technical review. The team completed a vibration check and monitored the shutdown logic to ensure it functioned as expected.

The GEnx-2B engine is optimized for the 747-8. The new engine contributes to a reduction in fuel burn, emissions and noise, which gives customers the lowest operating costs and best economics of any large passenger airplane while providing enhanced environmental performance.

 

asdnews.com

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: